Start date:
05/19/2024
Due date:
05/19/2024
% Done:
100%
Estimated time:
(Total: 5:30 h)
Spent time:
(Total: 5:30 h)
Description
For some specifications it would be good to see the references in all the specifications in one traceability matrix (for example, functional requirements could be mentioned in multiple documents).
Exact list of such "design inputs" it would be good to define in the project YAML file.
Updated by Oleksandr Ivanov 8 months ago
- Status changed from In Progress to Closed
Almirah gem version 0.1.8 was released