Actions
Feature #91
closedAggregated Traceability
Start date:
05/19/2024
Due date:
05/19/2024
% Done:
100%
Estimated time:
(Total: 5:30 h)
Spent time:
(Total: 5:30 h)
Description
For some specifications it would be good to see the references in all the specifications in one traceability matrix (for example, functional requirements could be mentioned in multiple documents).
Exact list of such "design inputs" it would be good to define in the project YAML file.
Updated by Oleksandr Ivanov 10 months ago
- Status changed from New to In Progress
Updated by Oleksandr Ivanov 10 months ago
- Status changed from In Progress to Closed
Almirah gem version 0.1.8 was released
Actions