Documents  Decision Records  Risks PRJR-001: Key Expertise Loss

PRJR-001: Key Expertise Loss

1 Status

Date Status
01-07-2026 Identified
03-07-2026 Analysed
05-07-2026 Mitigating

2 Description

The architecture and the deployment procedure live in the head of a single senior engineer. If that person leaves or becomes unavailable for an extended period, the team cannot release or change the core design without a long re-discovery phase.

3 Probability

4

4 Impact

4

5 Response

Reduce, by spreading the knowledge: pair the senior engineer with a second developer on every architecture change, and require the deployment procedure to be executed once per release by somebody else, following the written runbook only.

6 Affected Documents

# Proposed Text Req-ID
1 The architecture decisions shall be recorded in the requirements set rather than held informally. REQ-003

7 Monitoring

Review at every release: the risk stays open until two people have independently performed a production deployment within the last quarter.